SHRADHA APPATRMENT
SPECIFICATION
SUPER STRUCTURE:
RCC framed structure (M-25 grade) conforming to seismic zone II specifications.
WALLS:
First class K.B. Bricks will be used.
PLASTERING:
Walls will be finished with 12 mm thick plastering (1:6) mix.
FLOORING/TILE CLADDING:
All floors shall be done with Vitrified tile flooring, Glazed ceramic tiles shall be provided in the dado of toilets up to 4’-6” height. Kitchen cooking platform/sink shall be fixed with Cudappah. Glazed tiles will be provided over cooking platform up to 2’ toilets will have Anti-Skid Vitrified floor tiles and kitchen will have flooring with Kota stones.
DOORS & WINDOWS:
All the doorframes will be Sal wood of 4” x 2 ½” sections with factory made flush doors. Main door shall be of 3’-6” width and other doors- all factory made flush doors, will be 3’-0” width except toilets, which will be of 2’-6” width. Aluminum window frames and glaze panels along with aesthetically designed safety grills of Mild Steel will be provided at convenient places numbering 1 / 2 in each room as decided by the Developer.
ELECTRICAL:
Concealed wiring of Finolex / Anchor or equivalent make. Power plugs for fridge, T.V., phone etc. Individual meter boards, miniature circuit breakers (MCB) for each distribution board and modular switches of ISI standard.
CONNECTIVITY:
Telecom – telephone point in master bedroom/living area, intercom facility to all the units. Provision for cable T.V. Connection in master bedroom / living room.
SANITARY WORKS:
The toilets will have one Indian and other one Western W/C. Each toilet has one Towel rail; soap disc and necessary tap connections and sanitary fittings of ISI standard. One washbasin and face mirror will be provided in dinning / toilet(s).
PAINTS:
All exterior shall be provided with weather coats and interior shall be furnished with Wall putty. Doors and windows shall be furnished with required enamel paints.
WATER SUPPLY:
Common water supply arrangements (Deep Bore -well) will be provided as per the decision of the Developer. Supply line up to over-head tank/s with required capacity will be provided.
LIFTS:
High speed passenger lifts with rescue device will be provided by the Developer.
POWER BACK-UP:
D.G. set will be supplied for power back-up by the Developer.
COMPOUND WALL:
Decorated gated compound having 10” plastered brick wall up to 6’ height from ground level with designer gate/s of required dimension will be provided by the Developer.
DESCRIPTION OF LAND/BUILDING :
Dist. – Khurda, P.S.:Jatni, Tahasil – Bhubaneswar, under the jurisdiction of Dist.Sub-Registrar, Khurda, Bhubaneswar, Mouza – Alakara , Khata No.-229/8(Two hundred Twenty-nine/Eight),Sthitiban, Rev. Plot. No.- 505/597 (Five hundred Five /Five hundred Ninety-seven).
Approval :
Building plan approval (bearing no. – 336 dated 02 / 02 / 2007) obtained from Block Development Officer, Jatni vide letter dated 02 / 02 / 2007 issued by Panchayat Samiti Office, Jatni, Dist – Khurda.
SCHEDULE OF PAYMENT :
PRICE – @2700/sq.ft (987 sqft., 2BHK & 1 Toilet)
(1005 sqft., 2BHK & 2 Toilets)
(1022 sqft., 2BHK & 2 Toilets)
Reserve Parking Space ( Optional) – Rs. 2,50,000/- Extra
Initial Booking Amount – Rs. 1,00,000/-
Installment Stages |
Amount |
Booking Amount | 10% of flat cost |
Agreement Amount (Within 30days of Booking ) | 20% of total flat cost (Including Booking Amount) |
After Foundation Level | 20% of total flat cost |
After completion of Basement | 2.5% of total flat cost |
After Roof Slab of First Floor | 2.5% of total flat cost |
After Roof Slab of Second Floor | 2.5% of total flat cost |
After Roof Slab of Third Floor | 2.5% of total flat cost |
After Roof Slab of Fourth Floor | 2.5% of total flat cost |
After Roof Slab of Fifth Floor | 2.5% of total flat cost |
After Roof Slab of Sixth Floor | 2.5% of total flat cost |
After Roof Slab of Seventh Floor | 2.5% of total flat cost |
After Roof Slab of Eighth Floor | 2.5% of total flat cost |
After Roof Slab of Ninth Floor | 2.5% of total flat cost |
After Roof Slab of Tenth Floor | 2.5% of total flat cost |
Completion of Brick work of respective flat | 10% of total flat cost |
After Fitting of Choukath & Plastering | 10% of total flat cost |
At the time of Handover | 2.5% of total / remaining final payment of flat cost |
N.B. : Registration Cost, Proportionate Transformer / Electrification Cost, Service Tax (currently applicable @ 3.09% of total consideration amount) & Society Charges Extra.
Expected Handover : MID 2016 + 3 Months
Loan Assistance available. Project approved by HDFC, IDBI.